120.0 haRequired land
All projects
Flagship project · Demonstration record
Lucknow–Kanpur Expressway Expansion
Highway Uttar Pradesh Project ID: NLA-UP-2026-0148
Current stageCompensation & R&RProject authorityNational Highways Authority of IndiaLast updated25 Aug 2026, 14:42 IST
93.2 haAcquired · 77.7%
₹82.4 CrCompensation assessed
₹69.1 CrPaid · 83.9%
438Affected families
310R&R completed
Acquisition Progress
Stage-wise movement from proposed requirement to physical possession
GIS Parcel Map
Lucknow District · 64 mapped parcels · 120.0 ha
AcquiredCompensation pendingAwardedVerificationAttention
Loading secure GIS layers…
Acquisition Timeline
Planned statutory and administrative milestones
Proposal Created04 Mar 2026
District Scrutiny19 Mar 2026
State Approval08 Apr 2026
Notification23 Apr 2026
Awards16 Jun 2026
6Compensation31 Aug 2026
7R&R15 Sep 2026
8Possession30 Sep 2026
Parcels Requiring Attention
Priority records affecting the next milestone
| Parcel | Village | Area | Status | Compensation | |
|---|---|---|---|---|---|
| LU-142/3Survey 142/3 | Banthara | 1.84 ha | Compensation Pending | ₹41.2 L | |
| LU-143/1Survey 143/1 | Banthara | 2.12 ha | Acquired | ₹36.8 L | |
| LU-145/2Survey 145/2 | Bijnor | 1.36 ha | Awarded | ₹52.4 L | |
| LU-154/7Survey 154/7 | Bijnor | 1.29 ha | Disputed | ₹63.5 L |