National analytics

Acquisition Intelligence

Cross-programme analysis of progress, financial outcomes and delivery risk.

Acquisition Velocity
1,482 ha/mo
↑ 8.4%Six-month average
Average Project Delay
18.6 days
Down 2.4 days QoQ
High-Risk Projects
31
2.5% of active portfolio
Forecast Confidence
87.4%
Transparent rule coverage

National Acquisition Trajectory

Cumulative acquired land · thousand hectares

ActualPlanned

Portfolio Composition

By infrastructure category

1,248projects
Highways36%
Railways21%
Industrial16%
Energy15%
Other12%

State Outcome Comparison

Acquisition and compensation progress

AcquisitionCompensation

Stage Bottlenecks

Average processing days vs configured target

District scrutinyTarget 7 days
6.4dOn target
Field verificationTarget 10 days
11.8d+1.8 days
State reviewTarget 7 days
8.2d+1.2 days
Award declarationTarget 21 days
24.6d+3.6 days
CompensationTarget 30 days
38.4d+8.4 days

Transparent decision-support intelligence

Risk signals combine overdue milestones, pending compensation, disputed parcels, verification backlog, R&R trajectory and possession gaps. Scores support—never replace—administrative judgement.