Lucknow–Kanpur Expressway Expansion · Planned and actual administrative delivery.

Milestones completed5 / 862.5% workflow progress
Current stageCompensationDue 31 Aug 2026
Average delay2.2 daysCompleted milestones
Forecast slippage14 daysModerate risk signal

Administrative Milestone Register

Dates, status and recorded variance

MilestonePlanned DateActual / ForecastStatusVarianceEvidence
Proposal SubmissionStage 1 of 804 Mar 202604 Mar 2026CompletedVerified
District VerificationStage 2 of 818 Mar 202619 Mar 2026Completed1 dayVerified
State ApprovalStage 3 of 810 Apr 202608 Apr 2026Completed2 days earlyVerified
NotificationStage 4 of 822 Apr 202623 Apr 2026Completed1 dayVerified
Award DeclarationStage 5 of 810 Jun 202616 Jun 2026Completed6 daysVerified
Compensation CompletionStage 6 of 831 Aug 2026At RiskForecast +14Pending
R&R CompletionStage 7 of 815 Sep 2026At RiskForecast +9Pending
PossessionStage 8 of 830 Sep 2026PartialOn TrackPending