Project overview
Milestones & Timeline
Lucknow–Kanpur Expressway Expansion · Planned and actual administrative delivery.
Administrative Milestone Register
Dates, status and recorded variance
| Milestone | Planned Date | Actual / Forecast | Status | Variance | Evidence |
|---|---|---|---|---|---|
| Proposal SubmissionStage 1 of 8 | 04 Mar 2026 | 04 Mar 2026 | Completed | — | Verified |
| District VerificationStage 2 of 8 | 18 Mar 2026 | 19 Mar 2026 | Completed | 1 day | Verified |
| State ApprovalStage 3 of 8 | 10 Apr 2026 | 08 Apr 2026 | Completed | 2 days early | Verified |
| NotificationStage 4 of 8 | 22 Apr 2026 | 23 Apr 2026 | Completed | 1 day | Verified |
| Award DeclarationStage 5 of 8 | 10 Jun 2026 | 16 Jun 2026 | Completed | 6 days | Verified |
| Compensation CompletionStage 6 of 8 | 31 Aug 2026 | — | At Risk | Forecast +14 | Pending |
| R&R CompletionStage 7 of 8 | 15 Sep 2026 | — | At Risk | Forecast +9 | Pending |
| PossessionStage 8 of 8 | 30 Sep 2026 | Partial | On Track | — | Pending |