Bundelkhand Solar Corridor
Renewable Energy Uttar Pradesh Project ID: NLA-UP-2026-0091
Current stagePossessionProject authoritySECILast updated24 Aug 2026
718 haAcquired · 85.3%
₹314.8 CrCompensation approved
₹277 CrPaid · 88%
292Affected families
251R&R completed
Outcome Progress
Calculated from published project and parcel outcome records
Project Location
Jhansi, Uttar Pradesh · Aggregate marker
Loading secure GIS layers…
Acquisition Workflow
Current administrative position; milestone evidence remains in the timeline
ProposalCompleted
District ScrutinyCompleted
State ApprovalCompleted
NotificationCompleted
Award DeclaredCompleted
CompensationCompleted
R&R ProcessingCompleted
8Possession18 days in stage