Bundelkhand Solar Corridor

Renewable Energy Uttar Pradesh Project ID: NLA-UP-2026-0091

View map Documents
Current stagePossessionProject authoritySECILast updated24 Aug 2026
842 haRequired land
718 haAcquired · 85.3%
₹314.8 CrCompensation approved
₹277 CrPaid · 88%
292Affected families
251R&R completed

Outcome Progress

Calculated from published project and parcel outcome records

78.2% possession completed
Land acquired718
85.3%
Compensation paid277
88%
Field verification194
94.2%
R&R outcomes251
86%
Possession161
78.2%

Project Location

Jhansi, Uttar Pradesh · Aggregate marker

Open map

Loading secure GIS layers…

Acquisition Workflow

Current administrative position; milestone evidence remains in the timeline

Detailed timeline
ProposalCompleted
District ScrutinyCompleted
State ApprovalCompleted
NotificationCompleted
Award DeclaredCompleted
CompensationCompleted
R&R ProcessingCompleted
8Possession18 days in stage