Patna–Gaya Mobility Corridor

Highway Bihar Project ID: NLA-BR-2026-0131

View map Documents
Current stageAward DeclaredProject authorityNHAILast updated19 Aug 2026
394 haRequired land
246 haAcquired · 62.4%
₹278.1 CrCompensation approved
₹180.8 CrPaid · 65%
964Affected families
508R&R completed

Outcome Progress

Calculated from published project and parcel outcome records

37.2% possession completed
Land acquired246
62.4%
Compensation paid180.8
65%
Field verification101
58.7%
R&R outcomes508
52.7%
Possession64
37.2%

Project Location

Patna, Bihar · Aggregate marker

Open map

Loading secure GIS layers…

Acquisition Workflow

Current administrative position; milestone evidence remains in the timeline

Detailed timeline
ProposalCompleted
District ScrutinyCompleted
State ApprovalCompleted
NotificationCompleted
5Award Declared41 days in stage
6CompensationUpcoming
7R&R ProcessingUpcoming
8PossessionUpcoming