National Programme OfficeProjects
Project overview

Milestones & Timeline

Pune Regional Rail Expansion · Evidence-aware administrative stage register.

Stages completed4 / 850% workflow progress
Current stageAward Declared36 days in stage
Configured target21 daysFor the active stage
Schedule status15 days overdueRule-based threshold

Administrative Stage Register

Only evidence available in the current project record is shown

Project administrative workflow stage status
StagePositionStatusTimingEvidence
ProposalStage 1 of 8Before current stageCompleted—Stage completion recorded
District ScrutinyStage 2 of 8Before current stageCompleted—Stage completion recorded
State ApprovalStage 3 of 8Before current stageCompleted—Stage completion recorded
NotificationStage 4 of 8Before current stageCompleted—Stage completion recorded
Award DeclaredStage 5 of 836 days activeDelayed15d beyond targetNot available
CompensationStage 6 of 8Not startedUpcoming—Not available
R&R ProcessingStage 7 of 8Not startedUpcoming—Not available
PossessionStage 8 of 8Not startedUpcoming—Not available